07795 255 262

info@smarttraxrail.co.uk

Smarttrax Rail
Smarttrax Rail

Bawtry & East Cowton
Re-ballasting Works
Network Rail Works Delivery

Splitter

Smarttrax were asked to devise a plan to undertake re-ballasting works at both Bawtry and East Cowton on the East Coast Main Line by Network Rail. Both sites had failing formation in and around back to back crossovers. All remaining components were to be re-used.

View Diagram 1 View Diagram 2 View Staging WK 34

Example spec from East Cowton below:

Bawtry & East Cowton Project By Smarttrax Rail

Following initial site surveys plans were completed as below:

As well as the initial plan Smarttrax were responsible for:

All the planned works during 4 x 52 hr possessions were completed as planned and within timescales, ensuring that the lifespan of the cross overs were increased without the costs of a full S & C renewal including new components.

Removing crossing panel with PEM/LEMS

Bawtry & East Cowton Project By Smarttrax Rail

Installing temporary panels with Kirow 1200

Bawtry & East Cowton Project By Smarttrax Rail

Installing crossing panel with PEM/LEMS

Bawtry & East Cowton Project By Smarttrax Rail

Track reinstalled following formation works and reballast

Bawtry & East Cowton Project By Smarttrax Rail

Back to projects