07795 255 262

info@smarttraxrail.co.uk

Smarttrax Rail
Smarttrax Rail

Christon Road S & C Renewal
Renewal Of 1020ab Crossover & 1021a Right Hand Turn Out
Nexus Metro, Gosforth

Splitter

Smarttrax Rail were awarded the contract following the Tender process by NEXUS in early 2022. Delivery of the works was undertaken during 2 x 52hr Extended Control of Line (ECoL) possessions in February & March 2022.

The project involved the renewal of a crossover and right hand turnout with associated plain line and the installation of a new Rose Hill level crossing for vehicle use. No traditional engineering haulage could be used due to weight restrictions, therefore all materials had to be brought by road to a compound almost 4km from the site of works and then transported by rail with the reverse required for removal of spent materials and spoil. The S & C units were delivered to the compound in panel form and a plan to get them to site without breaking them down had to be devised. The solution was to tandem lift the units from the compound onto flat bed trailers with 2 x Superbug 300 machines, transport the units to site on the trailers and then re-lift and install with the 2 x Superbugs. Prior to the core works the machines were on site to complete test lifts for capacity and jib height due to low OHLE wires on site. This was the 1st time that this method had been utilised on the Nexus infrastructure and was completed as planned without any issues. Following the 2 ECoL possessions all the planned works were completed within timescales with all ITP’s signed and approved by the client. Further overnight possessions were utilised to complete all remaining follow up works with completion certificate issued by the client.

View Diagram View Video

Smarttrax undertook the role of Principle Contractor for the delivery and management of the package of works with the sole responsibility for the entire project. The installation of the new points and crossings were self-delivered by Smarttrax with sub-contractors engaged to complete associated specialist works. Smarttrax project management team including, PM, CEM, CRE track, HSQE and commercial managers were responsible the general day to day running of the project including:

Christon Road Stats

S&T support with Sigtech LTD

OHL Support with Keltbray LTD

Plant support with Story Plant Ltd & ready power super bugs


Back to projects