Bridlington Station Remodelling
Network Rail Works Delivery
Smarttrax Rail were contracted by NWR Works Delivery to produce a development plan to complete the track element of this signalling led project. Working in close collaboration with signalling staff the plan was completed and integrated to allow the seamless delivery of all aspects of the project.
The project was undertaken during an 11 day blockade. The purpose of the works was to simplify the layout by removing redundant points from the station area. This involved removal of 13 ends of points, the renewal of 3 new ends of points and 1200m of plain line track.
View Diagram View VideoOn completion of the development works Smarttrax then undertook key roles in:
Detailed planning:
- Production of hour by hour prep works and blockade timelines
- Ballast calculations
- Haulage plans
- Tamper plans
- Stressing plans
- Crane plans with Kirow staff
Prep works:
- Removal of redundant sidings to relieve time pressures during the blockade
- Delivery of loose S & C materials
- Build up of all S & C panels
- Installation of tracks where possible away from existing alignment
- Production of 3D machine control files
- Production of tamping geometry files
Delivery:
- Supply of all track engineers throughout the blockade on 3 shift 24hr pattern
- Supply of site management throughout the blockade on 3 shift 24hr pattern
- Production of site paperwork
- Weld installation supervision
- Tamping and production of live as built surveys including platform gauging
- Stressing
- CRT assessments and management
- Provision of all technical equipment including Trimble survey and machine control kit
- Track hand back
Follow up works:
- Completion of health & safety file
- Follow up tamps
- Track monitoring over weak underbridge structure
- Track hand back